Information for local authorities

The project falls under the Act on Accelerating the Construction of Transport, Water and Energy Infrastructure and Electronic Communications Infrastructure (the Line Act).

Property law preparation

More than 7,600 plots along the Dukovany-Bosonohy Nuclear Power Plant route

Land on the territory of the city of Brno more than 3 100 plots

Contract for the establishment of an easement (duration approx. 6 months)

Expropriation (duration approx. 6 months)

Contract for temporary land occupation during the construction of a hot water pipeline

Agreement on land entry and compensation for damaged crops

Permission
processes

The hot water pipeline route will be permitted within the framework of combined planning and construction proceedings 

Pipeline bridges over the Jihlava and Oslava rivers are part of the route (along the Temelín thermal feeder) 

Transfer stations will also be permitted structurally 

No landowner consent is required to issue an “interim” construction permit (construction included in the Line Act)